Shireoaks Village Hall with Lindrick Van

Shireoaks Village Hall Refurbishment is halfway through the project now and it is coming along nicely.

So far we have completed the rip out of the existing bar, central heating system, kitchen and washroom facilities and also removed the old plasterwork. As part of our remit we have installed a tanking membrane system to all walls and then boarded and plastered. Then we installed all new central heating piping and supplied and installed a new 60kw commercial boiler, where we have concealed the pipework in a false stud wall.

We have removed the existing kitchen, ladies, gentlemens, and disabled toilets. We then fitted a fully functioning new modern kitchen, as well as all new toilets, sinks, and hand dryers in all three toilets. A baby changing area has been created.

We are on course for full completion for 1st March 2019.